- March 2016- Trailer arrives.
- April 2016- Stud walls go up.
- June 2016- Roof is framed.
- July 2016- Electrical and plumbing going in walls.
- July 2016- Metal roof goes on.
- August 2016- House wrap, windows, door, and molding go on.
- September 2016- Lap siding starts going on.
- September 2016- Cedar shingles start going up.
- October 2016- Interior loft, walls, stairs framed.
- November 2016- Loft subfloor goes in.
- November 2016- Interior homemade shiplap starts to go up.
- December 2016- The last shingle goes up.
- December 2016- Exterior finished.
- December 2016- Stair drawers go in.
- February 2017- Shower walls go up.
- February 2017- Water heater installed and the beginning of painting interior.
- February 2017- Bathroom sink goes in.
- February 2017- Kitchen cabinets go in.
- February 2017- Ceiling boards go up.
- February 2017- More painting
- March 2017- Electrical wiring covered.
- March 2017- Countertops go in.
- March 2017- Pocket door installed.
- March 2017- Begin staining beams.
- March 2017- Stairs stained.
- March 2017- Flooring goes in.
- June 2017- Stairs stained and working.
- June 2017- Cabinet doors and hardware installed.
- June 2017- Ladder to master loft installed.
- Sitting/dining area and master loft with queen bed.
- August 2017- Interior finished and decorated.
- October 2017- Attempt to move house to the side yard, and it’s stuck.
- October 2017- Decided to park the house along our driveway.