March 2016- Trailer arrives.
-
-
April 2016- Stud walls go up.
-
-
June 2016- Roof is framed.
-
-
July 2016- Electrical and plumbing going in walls.
-
-
July 2016- Metal roof goes on.
-
-
August 2016- House wrap, windows, door, and molding go on.
-
-
September 2016- Lap siding starts going on.
-
-
September 2016- Cedar shingles start going up.
-
-
October 2016- Interior loft, walls, stairs framed.
-
-
November 2016- Loft subfloor goes in.
-
-
November 2016- Interior homemade shiplap starts to go up.
-
-
December 2016- The last shingle goes up.
-
-
December 2016- Exterior finished.
-
-
December 2016- Stair drawers go in.
-
-
February 2017- Shower walls go up.
-
-
February 2017- Water heater installed and the beginning of painting interior.
-
-
February 2017- Bathroom sink goes in.
-
-
February 2017- Kitchen cabinets go in.
-
-
February 2017- Ceiling boards go up.
-
-
February 2017- More painting
-
-
March 2017- Electrical wiring covered.
-
-
March 2017- Countertops go in.
-
-
March 2017- Pocket door installed.
-
-
March 2017- Begin staining beams.
-
-
March 2017- Stairs stained.
-
-
March 2017- Flooring goes in.
-
-
June 2017- Stairs stained and working.
-
-
June 2017- Cabinet doors and hardware installed.
-
-
June 2017- Ladder to master loft installed.
-
-
Sitting/dining area and master loft with queen bed.
-
-
August 2017- Interior finished and decorated.
-
-
October 2017- Attempt to move house to the side yard, and it’s stuck.
-
-
October 2017- Decided to park the house along our driveway.